Pedestrian Pathway Repairs Phases 2 and 3

Friday, August 2, 2024, 10:00am

TO: Campus Community
FR: J.Dana Twedell, AVP Facilities Management

As part of our ongoing infrastructure renewal efforts, this August we’ll be implementing Phases 2 and 3 of our campus pedestrian pathway improvements. The work will begin Monday, August 5, and be completed Friday, August 16. Please see area maps below for each phase.

Phase 2: Art, Stevenson, International Hall pathways, and North Lake

phase 2 copy.png

Phase 3: East Children’s School and Zinfandel

phase 3.png

Please contact Facilities Management with any questions at 707-664-2317.

Thank you.